Wellbore clean up
16/03/2016

Wellbore clean up is a critical component of any new well construction. Failure to adequately clean the wellbore can cause major difficulties in running the completion resulting in large amounts of NPT with all the associated costs. Conversely, performing over-complicated clean ups to ensure success adds additional risks and unnecessary extra cost.
 
This paper examines an operator's experience with wellbore  clean ups over a wide range of assets in the UK and Norwegian sectors of the North Sea. The operator wished to reduce the time taken by developing best practice guidelines. This would provide a common approach to wellbore clean up operations over all assets.
 
Using reports from 19 offshore wells completed between 2002 and 2004, the time taken during clean up operations was split between nine categories:
 
Running Tools
Chemical Clean up / Displacement
Pit Cleaning
Waiting on Equipment
Waiting on Weather
Pressure Testing
Non clean up Ops
Safety Events
Waiting on Permits
This allowed the causes of extended time to be identified and pinpointed the areas where most time could potentially be saved. Some of these were:
 
Clean up tool failures
Over-complicated tool-strings
Becoming stuck due to over ambitious toolstrings
Rig equipment failures
Incomplete tools being sent offshore
Repeating of chemical clean up due to wellbore filters being full of mud/debris
Delays while waiting for pit cleaning to be completed
Lessons not being learned from other assets
These and other causes were further examined and discussed by operator staff in a workshop and vendor interviews. Guidelines were then developed by combining existing good practices from different assets and other industry experience.
 
Benefits of Guidelines
 
Will provide uniform approach across all assets.
Lessons learned across assets are captured to ensure continuous improvement.
Aid development of less experienced Engineers.
Will reduce overall time of clean ups through consistent best practice use.
Reduced time = Reduced costs